/>

‘Low solar tariff viability depends on cost of debt’

Tariffs fell below ₹3 per unit at a recent bid

Updated - February 19, 2017 08:26 am IST - NEW DELHI:

Solar panels atop a building.

Solar panels atop a building.

The viability of solar projects at the historically low tariffs of about ₹3 realised recently would critically depend on the cost of long-term debt, and also the continuance of low prices of solar modules, according to a report by the rating agency ICRA.

The recently-concluded bid for three 250 MW units in the Rewa plant in Madhya Pradesh saw tariffs falling below ₹3 per unit, sparking some concern in the industry that tariffs were becoming unviably low.

“This signifies a major improvement in the cost competitiveness of solar energy against both alternate renewable as well as conventional energy sources,” according to the report.

“Viability of such tariff for project developer from its credit perspective will be critically dependent upon the availability of long tenure debt (up to 18-20 year post project completion date) at cost competitive rate as well as more importantly, its ability to keep the cost of PV (photovoltaic) modules within the budgeted levels,” Sabyasachi Majumdar, senior vice president and group head at ICRA Ratings said.

Debt service ratio

Any deviation in project parameters and cost assumptions could have an adverse impact on project returns and debt service ratios, according to the ICRA report.

“On the other hand, however, project developers may have an incremental upside arising out of their ability to improve the PLF level using trackers or by a further downward movement in equipment prices over the execution period,” Girishkumar Kadam, Vice President and Sector Head at ICRA Ratings said.

The report noted that such low tariffs in Madhya Pradesh were enabled by a few favourable and unique structures in the project power purchase agreements such as a State government guarantee for the contracted capacity by the utility as well as a compensation for deemed generation in case of non-availability of the grid.

“With competitive bidding route adopted for award of solar projects & fall in PV module price levels, cost competitiveness of solar PV bid tariff has thus significantly improved as evident in decline from ₹6.5/kwh in calendar year 2014 to ₹5.0/kwh in calendar year 2016, and further to ₹3.3/kwh for bidding of project capacity in the Rewa Solar Park,” the report added.

Wind vs thermal plants

Against this, the average feed-in tariff for wind energy and competitively bid thermal plants in the last 24 months has remained at ₹ 4.8/kwh and ₹4-5/kwh, respectively.

Mr. Majumdar added that a deemed generation clause along the lines of the Rewa bid if adopted at a policy level by the Ministry of New and Renewable Energy would be a positive for the solar and wind sectors given the incidences of states backing down from their commitments in the recent past.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.