‘The mega project is to be executed at a cost exceeding ₹650 crore and the work is expected to commence in October’

Published - August 24, 2018 07:21 am IST - Tiruchi

 The design of the proposed new passenger terminal building to come up at Tiruchi international airport.

The design of the proposed new passenger terminal building to come up at Tiruchi international airport.

With tendering process completed for the construction of the state-of-the-art passenger terminal building at the Tiruchi international airport and mandatory clearance having coming through from the Public Investment Board, the multi-crore project is expected to commence in October.

A leading Kolkata based construction company had quoted the lowest price in the bidding process for the multi-layered passenger terminal building construction project at the fast growing Tiruchi airport.

The Airports Authority of India (AAI) was in the process of awarding the work to the lowest bidder for the mega project to be executed at a cost exceeding ₹650 crore, a senior AAI official told The Hindu .

Alongside this development, the Public Investment Board of the Government of India headed by Secretary (Expenditure) has cleared funds to the tune of ₹930 crore for the construction of new passenger terminal building as well as for the construction of a new apron and a new Technical block – Cum – Air Traffic Control Tower at the Tiruchi airport, the official said.

The clearance from the Public Investment Board was mandatory for executing mega projects of the Central Ministries / Public Sector Undertakings.

With these developments taking place, the construction work of the futuristic terminal building was expected to commence in October, the official said.

The new building would come up adjoining the existing structure with the blueprint having already been readied by a French consultant engaged by the AAI.

The design of the new terminal building has been drawn up taking into account the peak hour demand and anticipating growth of passenger traffic over the next 15 years. It would come up on an area exceeding 60,000 square metres on the site owned by the AAI adjoining the existing terminal building with basement and air-side corridor.

Simultaneously, the AAI would soon be submitting the safety assessment pertaining to the terminal building project to obtain clearance from the Directorate General of Civil Aviation.

The AAI had obtained No-Objection Certificate (NOC) for height clearance for the new terminal building which would be about 35 metres.

With public hearing connected with the terminal building project having already been conducted at Tiruchi, the AAI authorities expect environment clearance to come through from the Union Ministry of Environment and Forests soon. The official said the AAI would now be in a position to spend for the project with the Public Investment Board having given its clearance.

As per the plan, the new terminal building would be completed in three years from the date of the award of contract.

The plan is to complete the work in 2021. The construction of the new apron would commence soon with the agency putting up a site office and mobilising materials for the proposed project.

The new apron would be in a position to accommodate 10 aircraft.

The site for the new Technical block – cum – Air Traffic Control Tower has been identified. The new ATC tower would be constructed in such way that the Air Traffic Controllers could have a 360 degree view, the official added.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.