The biomethanisation plant in Domlur is not the only wet waste management centre that has shut down. Nine other plants commissioned in 2014 were shut down by the first week of January after a tussle between the Bruhat Bengaluru Mahanagara Palike and the contractor.
The BMPP alleges that the contractor has not fulfilled its obligations, while the contractor claims that they have not been paid dues of ₹21.09 crore since December 2013. However, it is the residents who are the biggest losers in this fight, as wet waste which was handled locally in these plants are now being transported many kilometres away.
ADVERTISEMENT
ADVERTISEMENT
If the contractor fails to function as per standard operating procedure, the BBMP will take control of the plants. We will rope in RWAs if they show interest in managing the plants. — Sarfaraz Khan,Joint Commissioner (Solid Waste Management), BBMP “We want a biogas plant here as it would allow wet waste from at least two or three wards — Varthur, Hagathur and Kadugodi — to be processed locally,” said Anjali Saini, a member of Whitefield Rising, referring to the Varthur plant. This will reduce the incidence of garbage on the streets, she felt, as the pick-up vehicles could make trips in the evening as well. “At the moment, they have to go almost 50 km to drop the waste, so an additional trip is out of the question,” she explained. She felt the idea to bring in the RWAs was ill-conceived. “Why can’t the BBMP manage it on its own?”
In this case, the contractor claimed that the BBMP had not ensured water and electricity connections to the Varthur plant for two years.
ADVERTISEMENT
In Koramangala, a plant that has been closed for the past 10 days had been processing commercial waste from nearby restaurants. “It helped to manage the commercial waste and to light up lamps in the compound. We are planning to set up a similar plant for handling residential waste,” said Padmasree, president of the Koramangala RWA.