BBMP to go in for new tender for Ejipura elevated corridor

Work was to be completed in 30 months by November 2019, but is far from complete

Published - April 21, 2021 07:22 am IST

Just around 50% of work has been completed. Of the 81 pillars, only 67 have been constructed.

Just around 50% of work has been completed. Of the 81 pillars, only 67 have been constructed.

With nearly no progress for months, the Bruhat Bengaluru Mahanagara Palike (BBMP) has decided to terminate the tender for the Ejipura elevated corridor. The civic body will be floating a fresh tender to complete the 2.5-km elevated corridor.

BBMP Chief Engineer (Projects) N. Ramesh told The Hindu that the work, which was to be completed in 30 months by November 2019, is far from complete. Of the 81 pillars, only 67 have been constructed. Just around 50% of work has been completed. “We have already initiated the process of terminating the tender. We will have to float a global tender for the remainder of the work,” he said.

The work had been contracted to M/s Simplex Infrastructure Ltd. and the work order was issued in May 2017.

“Despite several notices to the contractor, there was no progress on the ground, which was inconveniencing many motorists and residents of surrounding areas,” said BBMP sources.

Incidentally, Bengaluru Metro Rail Corporation Ltd. (BMRCL) had terminated a contract with the company for pending work on an elevated section of the Pink Line on Bannerghatta Road. BMRCL floated a new tender and had pointed out that the contractor could not execute the work as per the tender conditions.

B.T.M. Layout MLA Ramalinga Reddy said that the elevated corridor, which was taken up at a cost of ₹203.20 crore, was initially planned to reduce traffic congestion, besides reducing commute time by at least 30 minutes.

“Several meetings were chaired by the BBMP Chief Commissioners and even the Administrator. The roads were in poor condition due to the ongoing work. For three years, there were no street lights on the 2.5-km stretch. The contractor just could not adhere to the tender conditions despite several notices,” he said, and added that he had utilised some special funds to repair the roads that had been dug up for shifting utilities, apart from installing new street lights along the entire stretch. “All that remains now is footpath repair. Hopefully, whoever bags the new tender will expedite the work.”

Seven junctions along the corridor

The elevated corridor from Ejipura to Kendriya Sadan will cover seven junctions – Ejipura Main Road-Outer Ring Road junction, Sony World junction, Kendriya Sadan junction, Koramangala 8th Main junction, Koramangala 60 feet road junction, Koramangala 5th Block, 1st A Cross junction, and Koramangala BDA junction. It is expected to ease vehicular movement to Tavarekere, M.G. Road, Halasoor Road, Agara, B.T.M. Layout, Koramangala, Sarjapur Main Road and Vivekanagar via Kendriya Sadan junction.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.