Tests are under way to ascertain the strength of 115 existing pillars of the 21-km long double decker Chennai Port-Maduravoyal elevated expressway.
“We will be using 115 of the 125 pillars. They have been incorporated into the fresh design. This is why testing their strength is important,” a source in the National Highways Authority of India (NHAI) said.
Samples of the core and steel rods are being lifted from each of the pillars. Ultrasonic and destructive tests are being carried out, so that the pillars can be retrofitted according to the new design. It will take two weeks to complete these tests.
Construction over Cooum River has been temporarily halted owing to the Northeast monsoon. “We had to remove temporary structures and pathways needed for the construction, to ensure free flow of rainwater,” an engineer associated with the project said.
The contracting company is also busy constructing the main carriageway and two ramps on the Chennai Port premises, where 700 metres of the expressway would come up. Simultaneously, at Maduravoyal and beyond, piling work is being carried out for a length of 640 metres.
The ₹3,570-crore project is being implemented under the engineering procurement construction mode, as part of the Bharatmala Pariyojana. Land acquisition is under way at Arumbakkam and Koyambedu. The work is being carried out in four packages.
The corridor will help connect the Chennai Port with the Chennai-Bengaluru Highway, and the industrial corridors at Sriperumbudur and Oragadam. The lower tier will carry urban traffic, and help decongest city roads. Entry and exit ramps would come up at 13 locations.
Published - November 22, 2024 01:13 am IST