60% of Perumbalam bridge project completed

The ₹100-crore project funded under KIIFB is expected to be completed in the first quarter of 2024

Published - September 15, 2023 07:39 pm IST - ALAPPUZHA

Construction of navigation spans of Perumbalam bridge in progress on Thursday.

Construction of navigation spans of Perumbalam bridge in progress on Thursday. | Photo Credit: HANDOUT

The construction of a bridge over Vembanad Lake connecting Perumbalam island to the mainland is making headway.

Officials said that 60% of the project had been completed. “Construction of 60 out of the total 81 girders has been completed. The construction of navigation spans and slabs is making steady progress. Measures are also underway to construct approach roads on both sides,” said an official.

The bridge will have 30 spans, including three navigation spans. Of these, 27 are constructed at a length of 35 m each, while the three in the middle are built at 55 m each. Once completed, the bowstring arch bridge will have a length of over 1,110 m and a width of 11 m. The width of the carriageway will be 7.5 m. Footpaths on both sides will have a width of 1.5 m.

The ₹100-crore project funded under the Kerala Infrastructure Investment Fund Board (KIIFB) is expected to be opened for traffic in the first quarter of 2024.

Officials said that approach roads with a total length of 650 m would be constructed. “Land acquisition for the construction of approach roads on Perumbalam and Vaduthala sides has been completed. The process of uprooting trees and clearing vegetation on the land has begun. Pending land piling work has also been started,” said the official.

Three bridges

The construction of the bridge was a long-pending demand of the people of Perumbalam, the only island grama panchayat in Alappuzha. The bridge will make travel hassle-free for around 15,000 islanders who currently use boats to commute between their village and the mainland. It is part of the government’s wider plan to connect the Cherthala-Arookutty road with the Vaikom-Poothotta-Tripunithura State Highway through Perumbalam island. In the next phase, the government plans to construct a bridge connecting Perumbalam island and Vattavayal island. A third bridge will be constructed between Vattavayal and Poothotta.

The construction of all three bridges is expected to make commuting easy between Ernakulam, Alappuzha and Kottayam districts.

The Perumbalam bridge project is being carried out by the Uralungal Labour Contract Cooperative Society.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.